- Vance Brand (CAPCOM)
-
Jim, could you switch your BIOMED switch to the position opposite to where it is now? We are getting a subcarrier, but no data. Over.
- Vance Brand (CAPCOM)
-
Okay. And we have a small addition to the procedure that was read up to you earlier, which involves power transfer from the LM to the CSM.
- Vance Brand (CAPCOM)
-
Okay. At the end of the procedure, after the step BAT 5 and 6, OFF, add the following: circuit breakers, panels—panels 11 and 16, ASCENT ECA CONTROL, both open. Over.
- Jim Lovell (CDR)
-
Okay. After the step BAT 5 and 6, OFF, step 3 will be circuit breakers panels 11 and 16 ASCENT ECA CONTROL, both open.
- Vance Brand (CAPCOM)
-
That's correct, Jim. And this is to guard against a single-point failure that—a remote possibility that would preclude you from getting the batteries back on.
- Jim Lovell (CDR)
-
Okay. We just had a battery warning MASTER ALARM, and it looks like it's battery 2.
- Vance Brand (CAPCOM)
-
Roger, Houston—This is Houston. Could you close the POWER AMP circuit breaker, and we'll get some high bit rate?
- Jim Lovell (CDR)
-
If you're getting high bit data, we could do an OFF/RESET and go back on on battery 2. We're standing by for that.
- Jim Lovell (CDR)
-
Say again. You want us to turn off battery 2, and leave it off until you look at it?
Expand selection up Contract selection down Close - Jim Lovell (CDR)
-
Okay. Battery 2 coming off the line.
Expand selection down Contract selection up - Vance Brand (CAPCOM)
-
Okay, Aquarius. So you want to stay in this configuration for awhile, and let's look at the battery.
- Vance Brand (CAPCOM)
-
13, Houston. We want to close the BAL LOADS circuit breaker on panel 16 now, again.